All issues spotted earlier have been corrected. They made a new change to the drawings: the height of our shower recesses went from 300mm to 350mm. This is because the dimensions on the plan are "from frame". So after adding plaster, waterproofing and tiles, the recesses will actually be about 300-310mm height (as stated in our contract).
Reading other people's blogs this is what we might expect to see in the coming months:
- February: peg out, excavation, piering and slab
- March: frame, plumbing, windows
- April: bricking
- May: gutters, main roof, brick cleaning
- June: cladding, garage & outdoor room roofs, electricals, doors & windows, gyprock, waterproofing
- July: cornices & skirting, cupboards, painting, wet area tiling
- August: garage door, pci
- September: handover
Good luck with it all..this is when it all starts to get exciting!!
ReplyDeleteCongratulations Christophe, it's a huge milestone, particularly with all the complications you've had to endure.
ReplyDeleteNow it's off the dodgem cars and onto the rollercoaster! :)
Thanks, guys! We are indeed very excited to finally move onto the next phase.